Each square metre of this product counts as 64.7 kg CO₂e over the modules its EPD declares: 60.5 to make it (A1–A3), 3.59 to deliver and place it (A4) and 0.664 at end of life.
Value per square metre, over the modules the EPD declares
64.7kgCO₂e/m²
EN 15804 modules A1 to A4 · Fossil only · GWP100 · AR5
Derived by open-climate.ai: the sum of EPD Ireland's published parts
The one scenario this EPD declaresReference year 2025
- Region
- Ireland IE
- Boundary
- Cradle to grave, embodied
- Data quality
- HighRated by us, not by the source
- Licence
- Open · EPD Ireland terms
- Declared by
- CareyGlass
Where 64.7 comes from
- A1-A3 Product stageDerived by open-climate.aiScope 3, cat. 160.593.4%
- Scope 3, cat. 43.595.5%
- End of lifeDerived by open-climate.aiScope 3, cat. 50.6641%
- Outside the scopes−20.4beside
Σ 64.7: the three declared modules add up to the total. D stays beside it.
Reporting this square metre under the GHG Protocol
This period
Scope 3, category 1 60.5 Scope 3, category 4 3.59
You buy the product for a building that is not yours. The product and its installation go to category 1, the delivery to category 4. The use stage belongs to the building owner; demolition waste you handle is category 5.
Later, when it happens
At end of life, in the year of demolition
- End of life Scope 3, category 5 0.664
Outside the scopes, reported separately
- D −20.4
A5, B1 to B7 and C1 to C4 are not declared: nothing to report.
The factor, standardised
Every factor on open-climate.ai answers the same questions in the same words, whatever the publisher. Open any ⓘ for the definition.
Materials › Glass and ceramics · Ireland · per m² · Supplier-specific
Cradle to grave, embodied · Fossil only · AR5
- BoundaryCradle to grave, embodiedThe whole life cycle EXCEPT the use stage: cradle_to_gate plus distribution to site, installation and end-of-life (EN 15804 A1-A3 + A4 + A5 + C1-C4). Learn more
- Cradle to grave, embodied
- Raw materials, inbound transport, fuel supply, fuel combustion, manufacturing, packaging, purchased energy, installation, outbound transport and end of life
- GWP methodWhich IPCC assessment report's warming potentials convert each gas to CO₂e, and over how many years the warming is counted (GWP100: 100 years). Learn more
- IPCC AR5, 100-year horizon
- Not on the record; set from EPD Ireland's method notes · impact method EF 3.0
- CO₂e basisWhich carbon the CO₂e counts. Fossil only leaves out biogenic CO₂ and land use; net total counts every pool, net of removals. The same activity on two bases is two different numbers. Learn more
- Fossil only
- Split by carbon origin, not by gas
- Life cycle
- Upstream: coveredProduction: coveredDownstream: partly coveredEnd of life: covered
High quality · Open licence · Any year
Module by module, up to the total
Seventeen EN 15804 modules, always in the same order. Each declared one moves the running total. D sits below zero after the total, because it is reported beside it.
beside the total, not in it
| Module | Name | Per square metre | Running total | Status |
|---|---|---|---|---|
| A1 | Raw material supply | 50.4452 | 50.4452 | Declared |
| A2 | Transport to the plant | 3.96062 | 54.4058 | Declared |
| A3 | Manufacturing | 6.08606 | 60.4919 | Declared |
| A4 | Transport to site | 3.58857 | 64.0805 | Declared |
| A5 | Installation | not declared | 64.0805 | Not declared |
| B1 | Use | not declared | 64.0805 | Not declared |
| B2 | Maintenance | not declared | 64.0805 | Not declared |
| B3 | Repair | not declared | 64.0805 | Not declared |
| B4 | Replacement | not declared | 64.0805 | Not declared |
| B5 | Refurbishment | not declared | 64.0805 | Not declared |
| B6 | Energy in use | not declared | 64.0805 | Not declared |
| B7 | Water in use | not declared | 64.0805 | Not declared |
| C1 | Demolition | not declared | 64.0805 | Not declared |
| C2 | Waste transport | 0.277139 | 64.3576 | Declared |
| C3 | Waste processing | 0.386882 | 64.7445 | Declared |
| C4 | Disposal | not declared | 64.7445 | Not declared |
| Total | EPD total, declared modules | 64.7445 | Sum of the declared modules | |
| D | Beyond the system boundary | −20.393 | not added | Beside the total, not in it |
What this number covers
Follow one square metre of this product through EN 15804's stages. The total counts what the EPD declares; what it leaves out stays visible.
A1-A3Product
Materials and making the product
Included60.5A4-A5Construction
Transport to site only; A5 not declared
A4 only3.59B1-B7Use
The product in service: maintenance, repair, replacement and the energy and water it uses
Not declaredC1-C4End of life
Waste transport and waste processing; C1, C4 not declared
C2, C30.664DBeyond the boundary
Recovery after end of life
Not in the total−20.4
Outside this boundary
- Maintenance
- Retail
- Use phase
- Recycling credit
Maintenance is out because B2 is not declared. The recycling credit is module D, shown beside the total.
Gases
- Fossil CO₂e64.7
- Biogenic CO₂e0.000373
- Land-use CO₂e0.0248
The total counts fossil CO₂e. EPD Ireland reports biogenic and land-use CO₂e separately; they are shown beside it, not added.
From EPD Ireland's record to a comparable factor
EPD Ireland publishes this EPD with one value per module. Each field as printed, and what open-climate.ai made of it.
The total and its modules
Use a module on its own when you report it in a different year or scope; never add one to the total.
About this factor
From EPD Ireland
What it is
Data quality: Time representativeness: The production year used in this LCA is 2023. The Ecoinvent version 3.9.1 database was used to represent energies, and wastes arising. This version of Ecoinvent was issued in March 2023. The main raw materials’ production data is from 2023 production. Time representativeness is thus assumed to be ‘Very Good’. Geographical representativeness: Data is from the area under study (Europe), where all the raw materials come from western Europe. The geographical representativeness is thus assumed to be ‘Very Good’. Technical representativeness: Data is from the processes and products under study. The same state of technology that is used by Carey Glass is that defined in the goal and scope. The processes at Carey Glass use electricity and diesel. The electricity record is for electricity generated by a mix of renewables and fossil fuel resources, plus own solar PV system. For the glass, there are two sources of EPD data: (1) Coated glass data is from a manufacturer-specific glass EPD of a production-weighted average of six coated glass products, from production locations in Europe. The market of applicability of these EPD is Europe. The primary data on this glass raw material is for the 2021 calendar year. (2) Clear Glass is from a manufacturer-specific and product-specific glass EPD for clear glass. The market of applicability of this EPD is Europe. The primary data on this glass raw material is for the 2021 calendar year. The technical representativeness is thus assumed to be ‘Good’. Allocation: The measurement of environmental impacts in this EPD uses the LCIA methodologies recommended for PEF 3.1. In this EPD, the waste processes are allocated in the relevant module. In the case of the use of secondary materials or energy recovered from secondary fuels, the system boundary between the system under study and the previous system (providing the secondary materials) is set where outputs of the previous system, e.g. materials, products, building elements or energy, reach the end-of-waste state. The modularity and the polluter payer principles have been followed. Cut-off criteria: All relevant inputs and outputs - like emissions, energy and materials - have been taken into account in this LCA, and in accordance with EN15804+A2:2019. The study covers at least 95% of the materials and energy per module and at least 99% of the total use of materials and energy of each unit process. Long term emissions have been excluded from the study.What it includes
the glass sheets are 6mm thick, and have a density of of 2,500 kg/m3. The void separating the two glass sheets is 20mm thick and is filled with argon gas. The U-value of the insulated glass unit is 1.1 W/m2.K.Where it applies
The insulated glass unit comprises one sheet of clear flat glass, one sheet of coated flat glass, filled with argon gas in the void. The unit is sealed with primary and secondary seals, and the glass sheets are separated and held in place by a spacer. The insulated glass unit is used as external and internal glazing in commercial and public sector buildings. The insulated glass unit is manufactured to the following technical standards: • Thermally toughened soda lime silicate safety glass according to EN 12150-1:2015+A1:2019 (for toughening individual glass panes). • Insulating glass unit according to EN 1279-1 (for assembly of final product).Source and licence
- Value
- Summed by open-climate.ai from its parts
- Publisher
- EPD Ireland (Irish Green Building Council)
- Published
- 2 October 2026
- Valid until
- 31 December 2030
The values and their metadata are served in full and may be reused with credit to the publisher.
Cite this factor
EPD Ireland (Irish Green Building Council), EPD data from https://epdireland.lca-data.com. Normalised by open-climate.ai, https://open-climate.ai/factors/libraries/epd_ireland/ (CC BY 4.0). https://open-climate.ai/factors/ef-epdireland-insulated_glass_unit_1m2-ie-m2-cradle_to_grave_embodied-30f1f8f7/?v=efv1-a609bccf5afa16866b890a1eef537280
Something looks wrong?
Tell us which value and why. We check it against the source and answer within a week.